General System-wide KPIs | Project Status Reporting, Project List and Program List
Tracking key performance indicators (KPIs) or measures is critical during a project. Providing the right data, at the right time, ensures the project stays on track.
This page describes KPIs that provide a consolidated, system-wide view of performance across the application. These KPIs support oversight and reporting at the organizational level and are used in areas such as Project Status Reporting, Project Lists, and Program Lists to track progress, health, and alignment across portfolios.
Note:
- Program Currency is displayed within the Program List.
- Company Currency is displayed in Project List and Project Status Report.
- Project Currency is displayed in Project List.
Tip: Use the Search box located above the table on the right corner to search for a KPI Name, Source, Currency or Description. The search returns the rows having your search term in either of the columns.
| Name | Source | Currencies | Project Status Reporting | Project List | Program List | Formula | Description | ||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Action Item | Work Process | N/A |
|
|
|
Action Item is the Count of Action Items on the Project. | |||||||||||||||||
| Actual Billable | Baseline |
|
|
|
|
(Sum(Actual Billable Time Amount) * Billing Rate) )+ Sum(Billable Expenses) + Sum(Billable Products) + Sum(Billable Charges) | Actual Billable is the Sum of all Billable Amounts on the Project. | ||||||||||||||||
| Actual Cost | Baseline |
|
|
|
|
Sum(Actual Payable Time Amount) * Cost Rate + Sum(Payable Expenses) + Sum(Payable Products) + Sum(Payable Money Charges) | Actual Cost is the Sum of all Cost Amounts on the Project. | ||||||||||||||||
| Actual Non-Billable | Baseline |
|
|
|
|
Actual Non-Billable is the Sum of all Non-Billable Amounts on the Project. | |||||||||||||||||
| Actual Time | Time | N/A |
|
|
|
Sum(Actual Billable Time) + Sum(Actual Non-Billable Time) + Sum(Actual Payable Time) + Sum(Actual Non-Payable Time). | Actual Time is the Sum of all Time Entries on the Project. | ||||||||||||||||
| Hard Booked Hours | Time | N/A |
|
|
|
All Hard Booked Hours is the Sum of all Hard Booked Hours on the Project. | |||||||||||||||||
| Soft Booked Hours | Time | N/A |
|
|
|
All Soft Booked Hours is the Sum of all Soft Booked Hours on the Project. | |||||||||||||||||
| Baseline Billable Budget | Baseline |
|
|
|
|
Baseline Billable Budget is the Sum of Baseline Billable Budgets of the Project. | |||||||||||||||||
| Baseline Cost Budget | Baseline |
|
|
|
|
Baseline Cost Budget is the Sum of Baseline Cost Budgets of the Project. | |||||||||||||||||
| Baseline Non-Billable Budget | Baseline |
|
|
|
|
Baseline Non-Billable Budget is the Sum of Baseline Non-Billable Budgets of the Project. | |||||||||||||||||
| Baseline Time Budget | Time | N/A |
|
|
|
Baseline Time Budget is the Sum of Baseline Time Budgets of the Project. | |||||||||||||||||
| Billable Charges | Baseline |
|
|
|
|
Sum(Milestone Billable Charges) + Sum(Recurring Billable Charges) + Sum(Product Billable Charges) + Sum(Money Billable Charges) | Billable Charges is the Sum of all Billable Charge Amounts on the Project. | ||||||||||||||||
| Billable Expenses | Baseline |
|
|
|
|
Sum(Billable Expenses) | Billable Expenses is the Sum of all Billable Expense Amounts on the Project. | ||||||||||||||||
| Billable Estimate To Completion | N/A |
|
|
|
Sum(billable booked hours in CWP) as in Financial Planner based on the FP settings which can be on Hard, soft or all booking | Estimate to Complete (ETC) KPI is the total number of billable Hours expected to spend in the future for a Project to be done | |||||||||||||||||
| Billable Hard Booked Hours | Time | N/A | Billable Hard Booked Hours is the Sum of all Billable Hard Booked Hours on the Project | ||||||||||||||||||||
| Billable Products | Baseline |
|
|
|
|
Sum(Billable Products) | Billable Products is the Sum of all Billable Product Amounts on the Project. | ||||||||||||||||
| Billable Soft Booked Hours | Time | N/A |
|
|
|
Billable Soft Booked Hours is the Sum of all Billable Soft Booked Hours on the Project | |||||||||||||||||
| Billable Time | Time | N/A |
|
|
|
Sum (Actual Billable Time) | Billable Time is the Sum of all Billable Time Entries on the Project. | ||||||||||||||||
| Billable Time Amount | Time |
|
|
|
|
Sum(Actual Billable Time Amount) * Billing Rate | Billable Time Amount is the Sum of all Billable Time Amounts on the Project. | ||||||||||||||||
| Bug | Work Process |
|
|
|
Bug is the Count of Bugs on the Project. | ||||||||||||||||||
| Current Billable Budget | Baseline |
|
|
|
|
Sum(Current Billable Time) + Sum(Current Billable Expenses) + Sum(Current Billable Charge) + Sum(Current Billable Product) | Current Billable Budget is the Sum of Current Billable Budgets of the Project. | ||||||||||||||||
| Current Cost Budget | Baseline |
|
|
|
|
Sum (Current Cost Time + Current Cost Expense + Current Cost Charge + Current Cost Product) | Current Cost Budget is the Sum of Current Cost Budgets of the Project. | ||||||||||||||||
| Current Cost Charge Budget in Project Cost Curr. | Baseline |
|
|
|
|
Sum (Current Cost Time + Current Cost Expense + Current Cost Charge + Current Cost Product) | Current Cost Budget is the Sum of Current Cost Budgets of the Project. | ||||||||||||||||
| Current Non-Billable Budget | Baseline |
|
|
|
|
Current Non-Billable Budget is the Sum of Current Non-Billable Budgets of the Project. | |||||||||||||||||
| Current Time Budget | Time | N/A |
|
|
|
[Sum(Current Time Billable Budget )]+ [ Sum (Current Time Non-Billable Budget)] | Current Time Budget is the Sum of Current Time Budgets of the Project. | ||||||||||||||||
| Estimate At Completion |
|
|
|
This is the Sum of Hours Expected to be Spent when the Project is Completed | |||||||||||||||||||
| Estimate To Completion |
|
|
|
Sum(booked hours in CWP) as in Financial Planner based on the FP settings which can be on Hard, soft or all booking | Estimate to Complete (ETC) KPI is the total number of Hours expected to spend in the future for a Project to be done | ||||||||||||||||||
| Forecasted Billing | Forecast |
|
|
|
|
Forecasted Billing is the Sum of all Forecasted Billing Amounts on the Project. | |||||||||||||||||
| Forecasted Cost | Forecast |
|
|
|
|
Forecasted Cost is the Sum of all Forecasted Cost Amounts on the Project. | |||||||||||||||||
| Incident | Work Process | N/A |
|
|
|
Incident is the Count of Incidents on the Project. | |||||||||||||||||
| Issue | Work Process | N/A |
|
|
|
Issue is the Count of Issues on the Project. | |||||||||||||||||
| Milestones | N/A |
|
|
|
Milestones is the Count of Milestones on the Project. | ||||||||||||||||||
| Non-Billable Estimate To Completion | N/A |
|
|
|
Sum(Non-Billable booked hours in CWP) as in Financial Planner based on the FP settings which can be on Hard, soft or all booking | Estimate to Complete (ETC) KPI is the total number of Non-Billable Hours expected to spend in the future for a Project to be done | |||||||||||||||||
| Non-Billable Hard Booked Hours | N/A |
|
|
|
Non-Billable Hard Booked Hours is the Sum of all Non-Billable Hard Booked Hours on the Project. | ||||||||||||||||||
| Non-Billable Soft Booked Hours | N/A |
|
|
|
Non-Billable Soft Booked Hours is the Sum of all Non-Billable Soft Booked Hours on the Project. | ||||||||||||||||||
| Non-Billable Time | Baseline | N/A |
|
|
|
Sum (Actual Non-Billable Time) | Non-Billable Time is the Sum of all Non-Billable Time Entries on the Project. | ||||||||||||||||
| Payable Charges | Baseline |
|
|
|
|
Sum(Payable Charge entries) | Payable Charges is the Sum of all Payable Charge Amounts on the Projected Cost Amounts on the Project. | ||||||||||||||||
| Payable Expenses | Baseline |
|
|
|
|
Sum(Payable Expenses) | Payable Expenses is the Sum of all Payable Expense Amounts on the Project. | ||||||||||||||||
| Payable Products | Baseline |
|
|
|
|
Sum(Payable Product entries) | Payable Products is the Sum of all Payable Product Amounts on the Project. | ||||||||||||||||
| Payable Time | Time | N/A |
|
|
|
Payable Time is the Sum of all Payable Time Entries on the Project. | |||||||||||||||||
| Payable Time Amount | Time |
|
|
|
|
Sum(Actual Payable Time Amount)* Cost Rate | Payable Time Amount is the Sum of all Payable Time Amounts on the Project. | ||||||||||||||||
| Prepaid Amount | Baseline |
|
|
|
|
Prepaid Amount is the Sum of positive Invoiced prepayment type Charge Entries associated to the PO line items on the Project. | |||||||||||||||||
| Project Survey | Work Process | N/A |
|
|
|
Project Survey is the Count of Project Surveys on the Project. | |||||||||||||||||
| Reimbursable Expenses | Baseline |
|
|
|
|
Reimbursable Expenses is the Sum of all Reimbursable Expense Amounts on the Project. | |||||||||||||||||
| Remaining PO Amount | Baseline |
|
|
|
|
Remaining PO Amount is the Total PO Amount less Total PO Invoiced Amount. | |||||||||||||||||
| Scope Change | Work Process | N/A |
|
|
|
Scope Change is the Count of Scope Changes on the Project. | |||||||||||||||||
| Service Request | Work Process | N/A |
|
|
|
Service Request is the Count of Service Requests on the Project. | |||||||||||||||||
| Skill Update Request | Work Process | N/A |
|
|
|
Skill Update Request is the Count of Skill Update Requests on the Project. | |||||||||||||||||
| Total Allocated Hours | Time | N/A |
|
|
|
Total Allocated Hours is the Sum of all allocated Hours on the Project | |||||||||||||||||
| Total Billable Allocated Hours | Time | N/A |
|
|
|
Total Billable Allocated Hours is the Sum of all Billable allocated Hours on the Project. | |||||||||||||||||
| Total Charges | Baseline |
|
|
|
|
Total Charges is the Sum of all Charge Amounts on the Project | |||||||||||||||||
| Total Expenses | Baseline |
|
|
|
|
Total Expenses is the Sum of all Expense Amounts on the Project. | |||||||||||||||||
| Total Invoiced | Baseline |
|
|
|
|
Total Invoiced is the Sum of all Invoiced Amounts on the Project | |||||||||||||||||
| Total Non-Billable Allocated Hours | Time | N/A |
|
|
|
Total Non-Billable Allocated Hours is the Sum of all Non-Billable allocated Hours on the Project. | |||||||||||||||||
| Total PO Amount | Baseline |
|
|
|
|
Total PO Amount is the Sum of all PO Line Item Amounts on the Project | |||||||||||||||||
| Total PO Consumed Amount | Baseline |
|
|
|
|
Total PO Consumed Amount is the Sum of all Billable approved Entries associated to POs on the Project. | |||||||||||||||||
| Δ Baseline Billable Budget* | Baseline |
|
|
|
|
Δ Baseline Billable Budget is the Difference between Baseline Billable Budget and Actual Billable | |||||||||||||||||
| Δ Baseline Cost Budget* | Baseline |
|
|
|
|
Δ Baseline Cost Budget is the Difference between Current Cost Budget and Actual Cost | |||||||||||||||||
| Δ Baseline Non-Billable Budget* | Baseline |
|
|
|
|
Δ Baseline Non-Billable Budget is the Difference between Baseline Non-Billable Budget and Actual Non-Billable | |||||||||||||||||
| Δ Baseline Time Budget** | Time |
|
|
|
Δ Baseline Time Budget is the Difference between Baseline Time Budget and Actual Time | ||||||||||||||||||
| Δ Current Billable Budget* | Baseline |
|
|
|
|
Δ Current Billable Budget is the Difference between Current Billable Budget and Actual Billable | |||||||||||||||||
| Δ Current Cost Budget* | Baseline |
|
|
|
|
Δ Current Cost Budget is the Difference between Current Cost Budget and Actual Cost | |||||||||||||||||
| Δ Current Non-Billable Budget* | Baseline |
|
|
|
|
Current Non-Billable Budget - Actual Non-Billable Budget | Δ Current Non-Billable Budget is the Difference between Current Non-Billable Budget and Actual Non-Billable | ||||||||||||||||
| Δ Current Time Budget* | Time | N/A |
|
|
|
Current Time Budget - Actual Time Budget | Δ Current Time Budget is the Difference between Current Time Budget and Actual Time | ||||||||||||||||
| % Consumed Budget Billable | N/A |
|
|
|
(Budget Total Billable Actual / Budget Total Billable Current ) * 100 | % Consumed Billable Budget KPI is the Percentage of all billable entries that occurred on the Project related to the planned Billable Budget. | |||||||||||||||||
| % Remaining Budget Billable | N/A |
|
|
|
(Budget Total Billable Delta Current / Budget Total Billable Current ) * 100 | % Remaining Billable Budget KPI is the Percentage of all billable entries that are not achieved yet on the Project related to the planned Billable Budget. | |||||||||||||||||
| Total Cost |
|
Total Cost = Actual Non-Labor Cost + Labor Cost Financial Planner Time and Material Method:
Financial Planner Percentage of Completion Method
|
Total Cost is the Sum of all Cost Amounts on the Project based on the settings in the Financial Planner | ||||||||||||||||||||
| Total Revenue |
|
When Recognized Revenue Row is NOT being displayed (Recognized Revenue is unchecked) or the Value for Recognized Revenue in the Database is NULL: Total Revenue = Revenue Sub-Total When Recognized Revenue Row is being displayed (Recognized Revenue row is checked)
Note: Revenue Sub-Total = Total Non-Labor Revenue |
Total Revenue is the Sum of all recognized Revenue or Non-Labor Revenue on the Project based on the settings in the Financial Planner |
Note: The value(s) are calculated using the most current conversion rate.