The synchronization is the Upland Project Planner (UPP) assignments bi-directionally integrating with Resource Management resource allocations. This process will allow for Bookings to co-exist within both Upland Project Planner as well as the Project Work Plan and for them to be maintained within the system of your choice.
This article covers how the synchronization of UPP assignments with Resource Management resource allocations, at the Project level, is activated.
Version Note: available as of Tenrox 2016 R1.8.
1. Access the Project
Tip: You can quickly open any of the recent ten existing Projects you've visited through the Home page, under the My Recent Projects frame.
2. Access the Project Options tab
The Project edit page will be displayed with an open General tab. Click the Options tab located next to it.