Field Name
|
Description
|
Type
|
Actuals To Include
|
This is the value set on the Forecast Setting (it can be Approved or All Entries )
|
|
Baseline Name
|
This is the name of the baseline. If it is the current baseline, it will display Project Name + Current else it will be the saved baseline name.
|
|
Baseline Type |
This is the baseline type and it can be set to 4 types of baselines: First Baseline, Last Baseline, Prior Baseline and Current Baseline. For the rest of the baselines, the value will be set to empty. |
|
Cost Forecast Method
|
This is the value set on the Forecast Setting under Forecast Methods section > Cost Field
|
|
Created On
|
This is the date when the baseline was created. If it is current baseline, the date that it was created for the first time and if it is saved, the date that it was last saved.
|
|
Created On Month
|
This is the date when the baseline was created. (Aggregate Date - Month).
|
|
Created On Month Year
|
This is the date when the baseline was created. (Aggregate Date - Month Year).
|
|
Created On Quarter
|
This is the date when the baseline was created. (Aggregate Date - Quarter)
|
|
Created On Quarter Year
|
This is the date when the baseline was created. (Aggregate Date - Quarter Year)
|
|
Created On Year
|
This is the date when the baseline was created.(Aggregate Date - Year)
|
|
Description |
This is the description of the baseline
|
|
Display Total Column
|
This is the value set on the Forecast Setting under Other Settings section > Display Total Column field
|
|
Display View
|
This is the value set on the Forecast Setting under View section > Display By field. This can be modified also from the financial planner page at the project level
|
|
Forecast Start
|
This is the Forecast Start Date calculated the last time the baseline was processed either manually or automation, based on the View setting (Start date based on current week, End date based on Current week, Start date of displaying period)
|
|
Forecast Start Month
|
This is the Forecast Start Date (Aggregate Date - Month).
|
|
Forecast Start Month Year
|
This is the Forecast Start Date (Aggregate Date - Month Year).
|
|
Forecast Start Quarter
|
This is the Forecast Start Date (Aggregate Date - Quarter)
|
|
Forecast Start Quarter Year
|
This is the Forecast Start Date (Aggregate Date - Quarter Year)
|
|
Forecast Start Year
|
This is the Forecast Start Date (Aggregate Date - Year)
|
|
Grand Total Average Revenue Rate In Base Curr
|
Calculated formula: Grand Total Role Revenue Amount in Base Currency / Grand Total Billable Time in Base Currency |
|
Grand Total Average Revenue Rate In Client Curr |
Calculated formula: Grand Total Role Revenue Amount in Client Currency / Grand Total Billable Time in Client Currency |
|
Grand Total Billable Time
|
Sum of the Billable Time calculated over the length of the whole project on the Combined view
|
|
Grand Total Charge Cost Amount In Base Curr
|
Sum of the Charge Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Charge Cost Amount In Client Curr
|
Sum of the Charge Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Charge Revenue Amount In Base Curr
|
Sum of the Charge Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Charge Revenue Amount In Client Curr
|
Sum of the Charge Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Cost Amount In Base Curr
|
Sum of the Combined Cost amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Cost Amount In Client Curr
|
Sum of the Combined Cost amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Expense Revenue Amount In Base Curr
|
Sum of the Expense Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Expense Revenue Amount In Client Curr
|
Sum of the Expense Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Amount In Base Curr
|
Sum of the Margin Total amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Amount In Client Curr
|
Sum of the Margin Total amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Charge Amount In Base Curr
|
Sum of the Margin Charge Total amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Charge Amount In Client Curr
|
Sum of the Margin Charge Total amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Charge Percentage By Cost
|
This is the Margin Charge Percentage by Cost calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Charge Percentage By Revenue
|
This is the Margin Charge Percentage by Revenue calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Percentage By Cost
|
This is the Margin Percentage by Cost calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Percentage By Revenue
|
This is the Margin Percentage by Revenue calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Role Amount In Base Curr
|
Sum of the Margin Role Total amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Role Amount In Client Curr
|
Sum of the Margin Role Total amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Role Percentage By Cost
|
This is the Margin Role Percentage by Cost calculated over the length of the whole project on the Combined view
|
|
Grand Total Margin Role Percentage By Revenue
|
This is the Margin Role Percentage by Revenue calculated over the length of the whole project on the Combined view
|
|
Grand Total Net Labor Amount In Base Curr
|
Grand Total Labor Revenue - Grand Total Cost Labor in Base Currency |
|
Grand Total Net Labor Amount In Client Curr
|
Grand Total Labor Revenue - Grand Total Cost Labor in Client Currency |
|
Grand Total Net Non Labor Amount In Base Curr
|
Grand Total Non-Labor Revenue - Grand Total Non-Labor Cost in Base Currency |
|
Grand Total Net Non Labor Amount In Client Curr
|
Grand Total Non-Labor Revenue - Grand Total Non-Labor Cost in Base Currency |
|
Grand Total Net Margin Amount In Base Curr
|
Grand Total Revenue - Grand Total Cost in Base Currency |
|
Grand Total Net Margin Amount In Client Curr |
Grand Total Revenue - Grand Total Cost in Client Currency |
|
Grand Total Net Margin Percentage
|
Net % Margin = (Grand Total Net Margin / Grand Total Revenue) * 100
|
|
Grand Total Net Margin Percentage Labor
|
Net Labor % Margin = (Grand Total Net Labor Margin/Grand Total Revenue Labor for the Actual Periods up to the Forecast Start Date) * 100
|
|
Grand Total Net Margin Percentage Non Labor
|
Net Non-Labor % Margin = (Grand Total Net Non-Labor Margin/Grand Total Non-Labor Revenue) * 100
|
|
Grand Total Non Billable Time
|
Sum of the Non Billable Time calculated over the length of the whole project on the Combined view
|
|
Grand Total Payable Time
|
Sum of the Payable Time calculated over the length of the whole project on the Combined view
|
|
Grand Total Percentage Complete
|
Calculated formula: Total Actual Billable Time Current Included / Grand Total Billable Time
|
|
Grand Total Percentage Non Billable
|
Calculated formula: Total Actual Non Billable Time Current Included / Grand Total Time
|
|
Grand Total Product Revenue Amount In Base Curr
|
Sum of the Product Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Product Revenue Amount In Client Curr
|
Sum of the Product Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Recognizable Amount In Base Curr
|
Sum of the Recognizable Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Recognizable Amount In Client Curr |
Sum of the Recognizable Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Recognized Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Recognized Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Recognized Labor Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Recognized Labor Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Recognized Non Labor Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Recognized Non Labor Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Grand Total Revenue Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Revenue Amount In Client Curr
|
Sum of the Combined Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Role Cost Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Role Cost Amount In Client Curr
|
Sum of the Combined Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Role Revenue Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Role Revenue Amount In Client Curr |
Sum of the Combined Revenue amounts in Client Currency calculated over the length of the whole project on the Combined view
|
|
Grand Total Time
|
Sum of the Time calculated over the length of the whole project on the Combined view on the Combined view
|
|
Is Current Baseline
|
Defines whether the baseline is current. It will show Yes for current baseline and No for other baselines
|
|
Reason
|
This is the Reason set when creating the baseline.
|
|
Revenue Forecast Method
|
This is the value set on the Forecast Setting under Forecast Methods section > Revenue Field
|
|
Total Actual Billable Time
|
Sum of the Billable Time calculated for the Actual period up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Billable Time Current Included
|
Sum of the Billable Time calculated for the Actual period up to the Start Date of the Current Period including the actuals from the current period on the Combined view
|
|
Total Actual Charge Cost Amount In Base Curr
|
Sum of the Charge Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Charge Cost Amount In Client Curr
|
Sum of the Charge Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Charge Revenue Amount In Base Curr
|
Sum of the Charge Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Charge Revenue Amount In Client Curr
|
Sum of the Charge Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Cost Amount In Base Curr
|
Sum of the Combined Cost amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Cost Amount In Client Curr
|
Sum of the Combined Cost amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Expense Revenue Amount In Base Curr
|
Sum of the Expense Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Expense Revenue Amount In Client Curr |
Sum of the Expense Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Amount In Base Curr
|
Sum of the Margin Total amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Amount In Client Curr
|
Sum of the Margin Total amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Charge Amount In Base Curr
|
Sum of the Margin Charge Total amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Charge Amount In Client Curr
|
Sum of the Margin Charge Total amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Charge Percentage By Cost
|
This is the Margin Charge Percentage by Cost calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Charge Percentage By Revenue
|
This is the Margin Charge Percentage by Revenue calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Percentage By Cost
|
This is the Margin Percentage by Cost calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Percentage By Revenue
|
This is the Margin Percentage by Revenue calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Role Amount In Base Curr
|
Sum of the Margin Role Total amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Role Amount In Client Curr
|
Sum of the Margin Role Total amounts in Client Curr calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Role Percentage By Cost |
This is the Margin Role Percentage by Cost calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Margin Role Percentage By Revenue
|
This is the Margin Role Percentage by Revenue calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Net Labor Amount In Base Curr
|
Total Actual Labor Revenue - Total Actual Cost Labor in Base Currency |
|
Total Actual Net Labor Amount In Client Curr
|
Total Actual Labor Revenue - Total Actual Cost Labor in Client Currency |
|
Total Actual Net Margin Amount In Base Curr
|
Total Actual Revenue - Total Actual Cost in Base Currency |
|
Total Actual Net Margin Amount In Client Curr |
Total Actual Revenue - Total Actual Cost in Client Currency |
|
Total Actual Net Margin Percentage
|
Net % Margin = (Total Actual Net Margin/Total Actual Revenue) * 100
|
|
Total Actual Net Margin Percentage Labor
|
Net Labor % Margin = (Total Actual Net Labor Margin/Total Actual Labor Revenue) * 100
|
|
Total Actual Net Margin Percentage Non Labor
|
Net Non-Labor % Margin = (Total Actual Net Non-Labor Margin/Total Actual Non-Labor Revenue) * 100
|
|
Total Actual Net Non Labor Amount In Base Curr
|
Total Actual Non Labor Revenue - Total Actual Cost Non Labor in Base Currency |
|
Total Actual Net Non Labor Amount In Client Curr
|
Total Actual Non Labor Revenue - Total Actual Cost Non Labor in Client Currency |
|
Total Actual Non Billable Time
|
Sum of the Non Billable Time calculated for the Actual period up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Non Billable Time Current Included
|
Sum of the Non Billable Time calculated for the Actual period up to the Start Date of the Current Period including the actuals from the current period on the Combined view
|
|
Total Actual Payable Time
|
Sum of the Payable Time calculated for the Actual period up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Payable Time Current Included
|
Sum of the Payable Time calculated for the Actual period up to the Start Date of the Current Period including the actuals from the current period on the Combined view
|
|
Total Actual Product Revenue Amount In Base Curr
|
Sum of the Product Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Product Revenue Amount In Client Curr
|
Sum of the Product Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Recognizable Amount In Base Curr
|
Sum of the Recognizable Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Recognizable Amount In Client Curr
|
Sum of the Recognizable Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Recognized Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Recognized Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Recognized Labor Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Recognized Labor Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Recognized Non Labor Amount In Base Curr
|
Sum of recognized revenue in Base Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Recognized Non Labor Amount In Client Curr
|
Sum of recognized revenue in Client Currency from starting the project up to Current Period on the Combined view
|
|
Total Actual Revenue Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Revenue Amount In Client Curr
|
Sum of the Combined Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Role Cost Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Role Cost Amount In Client Curr
|
Sum of the Combined Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Role Revenue Amount In Base Curr
|
Sum of the Combined Revenue amounts in Base Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Role Revenue Amount In Client Curr
|
Sum of the Combined Revenue amounts in Client Currency calculated up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Time
|
Sum of Time calculated for the Actual period up to the Start Date of the Current Period on the Combined view
|
|
Total Actual Time Current Included
|
Sum of Time calculated for the Actual period up to the Start Date of the Current Period including the actuals from the current period on the Combined view
|
|