Project Portfolio Gantt Report

The Project Portfolio Gantt report provides a graphical view of Project Schedules, Milestones, and overall progress for a custom selection of Projects.

The top-left hand corner of the report (directly under the title) displays some metadata about the report, such as the user who ran it, the date it was run, and the type of data it captures.

Note: The procedure below provides explanations of what this data means ("Gantt Style", "Milestone Style", etc.).

The left-hand side of the table includes columns that display information about each Project included in the report ("Name" to "End Date" in the example above). Users can determine which columns to include while running the report.

This page covers the following topics:

 

Progress Bar

Directly to the right of the Project information columns is the Gantt chart. It displays the current progress for each listed Project.

The bar on top (the green and blue bar in the example above) will extend from the Project's Start Date to its End Date. The green portion of the bar reflects the overall percent complete of the Project.

Example: In the image above, we can see that half of the progress bar is green. This is because the Project is 50% complete.

Note: The progress will not be adjusted for the start and end dates of the report itself. If the green portion of the bar does not seem to reflect the Project's current percent complete, it is probably because the entire Project duration is not displayed in the Gantt chart.

 

Baseline Bar

Directly under the progress bar is a gray bar that represents the Project's current Baseline.

Note: Baselines will only be included if the "Gantt Style" is set to "Tracking" while configuring the report's "Options". If not, the Baseline bar will not appear and the progress bar will not turn red if it surpasses the current Baseline.

In the image above, notice that the Baseline bar extends one day beyond the progress bar; this suggests that the Project duration was shortened by a day since the Baseline was captured.

If the Project is either on track to meet the Baseline or ahead of the Baseline, the non-green portion of the progress bar will be blue (like the image above). If the duration goes past the Baseline, however, the blue portion of the progress bar will turn red, indicating that the Project is no longer on track to meet the original Baseline end date.

Note: Baselines will only be included if the "Gantt Style" is set to "Tracking" while configuring the report's "Options". If not, the Baseline bar will not appear and the progress bar will not turn red if it surpasses the current Baseline.

 

Milestones

Users can choose to include Milestones in the Gantt chart. Each Milestone will be displayed as a diamond.


This diamond represents a Milestone with an end date of September 20th.

If the Milestone's end date has passed and it has not been completed, the diamond will turn red.

If the user chooses a "Milestone Style" of "Embedded" while configuring the report's "Options", the Milestone diamonds will appear directly within the progress bar (like above). On the other hand, selecting a "Milestone Style" of "Expanded" will create additional spreadsheet rows for each Milestone.

Note: Only the "Start Date", "End Date", and "Days" columns will expose data for Milestone rows.

 

Running the Project Portfolio Gantt Report

Eclipse PPM users can run the Project Portfolio Gantt report from the Reports page.

 

To run the Project Portfolio Gantt Report:

Before You Start: Projects will only be included in the report if the user running the report has the "Profile Details - View" permission on at least one of the Project's Policies. Additionally, the user will need the "Project Schedule - View" permission on at least one of the Project's Policies in order for the Project data to actually appear on the report. Consider this before tasking an Eclipse PPM user with running this report.

  1. Select the Reports icon from the Navigation Menu.

  2. Select Project Portfolio Gantt from the list of Eclipse Reports.

  3. Edit the basic report details at the top of the "Project Portfolio Gantt" window.

    • Title: Enter a custom name for your Project Portfolio Gantt report. This name will be displayed at the top of the report.

    • Format: Ignore this field for this report; the only available export option is a Microsoft Excel file.

  4. Edit the "Options" for your report.

  5. Select the Columns tab.

  6. Edit the "Columns" settings for your report.

  7. Select the Sorting tab.

  8. Edit the "Sorting" settings for your report.

    Note: Sorting refers to arranging Projects in a specific sequence based an attribute. It organizes the list of Projects in a linear order, either ascending or descending. Grouping, on the other hand, refers to clustering Projects in the report by shared characteristics. See Step 10 for information on the report's "Grouping" settings.

  9. Select the Grouping tab.

    Note: Grouping refers to clustering Projects in the report by shared characteristics. Sorting, on the other hand, refers to arranging Projects in a specific sequence based an attribute. It organizes the list of Projects in a linear order, either ascending or descending. See Step 8 for information on the report's "Sorting" settings.

  10. Select the Run button.

After selecting Run, the report will automatically download onto your device in a Microsoft Excel spreadsheet.