WIP Policy Rule Types

There are three rule types for revenue recognition:

  1. Time and Materials rule
  2. Fixed Price with Average Rate rule
  3. Percent Complete rule

This article explains the three rule types for revenue recognition and outlines key rule dynamics such as currency use and update restrictions.

Rule Dynamics:

Some important rule dynamics are followed in recognizing revenue. These include:

  • All revenue within the rules is referred to in the Client Currency.
  • The Rule Type cannot be updated if there are any Accrual Batches created for the Project.
  • The WIP Account and Revenue Account can be updated.

Time and Materials Rule

With this rule, revenue is recognized as (and when) work is performed (when a billable entry is approved) for the project. For example, if Employee X goes on-site for 10 hours and their billable rate is 100$/hour, then $1000 is recognized as revenue.

Fixed Price with Average Rate Rule

With this rule, revenue recognition is based on the percentage of completion between the time budget defined and the actual time using an average rate.

This rule only accounts for approved billable entries of type Time for all the Project's Tasks (including suspended and decommissioned tasks).

For example, Employee X defines an average rate of 100$ and a time budget of 100 hours. Come accrual time, if Employee X has done 80 hours of billable work, then their percent complete is 80% and the revenue to recognize is 8,000$ (80 hours * 100$ average rate)

Percent Complete Rule

With this rule, you recognize an amount of the project milestone billing rule based on the Milestone percentage of completion (specified on the Milestone Edit page.

WIP Accrual Batch Exclusions

This feature prevents including entries that have an associated Revenue Recognition Schedule from being included in the WIP Accrual Batch.

When a policy of type Time and Materials exists on the Project, the WIP Accrual Batch excludes:

  • Approved billable Charge entries that have an associated Revenue Recognition Schedule.
  • Approved billable Product entries that have an associated Revenue Recognition Schedule.
  • Approved billable Time, Expense, Charge or Product entries that are included in a Project level Revenue Recognition Schedule (through the Apply toTime/Expense/Charge/Product entries between Project start/Custom and Project end/Custom option).

When a policy of type Time and Materials exists on the Project, the WIP Accrual Batch is flagged for an update when:

  • A Charge entry included in the Batch has a Revenue Recognition Schedule associated to it.
  • The Revenue Recognition Schedule of a Charge entry, that was not included in the WIP Batch because it had a Revenue Recognition Schedule associated, is deleted.
  • A Product entry included in the Batch has a Revenue Recognition Schedule associated to it.
  • The Revenue Recognition Schedule of a Product entry, that was not included in the WIP Batch because it had a Revenue Recognition Schedule associated, is deleted.
  • A Time, Expense, Charge or Product entry that is included in a WIP Accrual Batch becomes included in the Project's Revenue Recognition Schedule (through the Apply toTime/Expense/Charge/Product entries between Project start/Custom and Project end/Custom option).
  • A Time, Expense, Charge or Product entry that was not included in a WIP Accrual Batch because it was included in the Project's Revenue Recognition Schedule (through the Apply toTime/Expense/Charge/Product entries between Project start/Custom and Project end/Custom option) gets excluded from the Project's Revenue Recognition Schedule (either through the entry type change or through the date change).

When a policy of type Time and Materials exist on the Project, the WIP Accrual Batch will not be flagged for an update when:

  • A Charge entry is updated and that entry has an associated Revenue Recognition Schedule.
  • A Product entry is updated and that entry has an associated Revenue Recognition Schedule.
  • A Time, Expense, Charge or Product entry is updated and that entry is included in the Project's Revenue Recognition Schedule (through the Apply to Time/Expense/Charge/Product entries between Project start/Custom and Project end/Custom option).

There will be no changes made to the functionality of the WIP Accrual Batch when a WIP Policy of type Percent Complete or Fixed Price with Average Rate is defined.